A solid solution
Project time frame

2016-2019

Client

HOFOR

Consultant

MOE

Concrete contractor

Per Aarsleff A/S

Amagerværket BIO4 plant

The construction of the BIO4 project was launched in September 2016, and the block is expected to be ready for operation starting in April 2019. High-efficiency combined heat and power (CHP) is an important part of an effective energy system. Today, Amagerværket is a cornerstone in the district heating supply in Copenhagen and also produces heat for a number of neighbouring municipalities. With a high-tech CHP block running on sustainable biomass, Amagerværket will take on even greater significance for the overall district heating system in the capital region.

Marlon products applied

Element Concrete PF70

Approx. 115 tons

Grout EKF 604LM

Approx. 117 tons Sommer/Vinter

Recent cases

BaseCamp Skovbrynet in Lyngby

Landing stage in Fredericia

Sønderparken Ikast

Silkeborghus