After many years in saltwater, the foundation beneath this private homeowner association’s landing stage in Fredericia was about to collapse. Extreme wear of both concrete and reinforcement just below the water line would have major consequences if something was not done fast. Instead of removing the bridge, the association chose to recast all the existing concrete pillars using Marlon Underwater Concrete. After cleaning the old pillars, a stainless reinforcement net was re-established. Afterwards, a form was erected, and divers pumped Marlon Underwater Concrete into the form from below and up until the form was completely filled and without air pockets. The bridge can now be used for many years to come.