A solid solution
Project time frame
July-September 2015
Contractor
CG Jensen A/S
Consultant
Bro Consult
Client
Brøndby Kommune
Renovation of bridge across Avedøre Havnevej
The bridge received new damp-proofing insulation, and the concrete was repaired on the upper and lower sides of the bridge. Moreover, moisture escape recesses have been mounted. The renovation work involved the replacement of damp-proofing material, which protects the concrete construction from water and moisture. This meant that the bridge pavement needed replacing. Additionally, the existing bridge bearings were replaced, and the concrete damage underneath the bridge, the end abutment and the box girders was repaired.